Chapter 17 – Project Management
88. A project has the activities and activity times (days) listed below. Determine the
probability that the project will require more than 15 days from start to finish.
89. Activity D has an optimistic time of 3 days, a pessimistic time of 9 days, and a most likely
time of 4 days. Determine its expected time and variance.
Chapter 17 – Project Management
1742
90. What is the probability that this project will take more than 10 weeks to complete if the
activity means and standard deviations are as shown below:
Chapter 17 – Project Management
91. The expected duration of this project is:
92. The critical path for the network shown is:
Chapter 17 – Project Management
93. The expected duration of this project is:
Chapter 17 – Project Management
94. The critical path for the network shown is:
95. What is the estimated expected (mean) time for activity E?
Chapter 17 – Project Management
96. What is the estimated standard deviation in the time for activity E?
97. What is the estimated expected (mean) time for project completion?
Chapter 17 – Project Management
1747
98. What is the estimated slack time for activity A?
99. What is the probability that this project will be completed within 205 days?
Chapter 17 – Project Management
100. What is the estimated expected (mean) time for activity D?
101. What is the estimated standard deviation in the time for activity D?
Chapter 17 – Project Management
102. What is the estimated expected (mean) time for project completion?
103. What is the estimated slack time for activity D?
Chapter 17 – Project Management
104. What is the probability that this project will be completed within 130 days?
105. What is the estimated expected (mean) time for activity E?
Chapter 17 – Project Management
106. What is the estimated standard deviation in the time for activity E?
107. What is the estimated expected (mean) time for project completion?
Chapter 17 – Project Management
1752
108. What is the estimated slack time for activity D?
109. What is the probability that the critical path for this project will be completed within 210
days?
Chapter 17 – Project Management
110. What is the estimated expected (mean) time for Activity E?
111. What is the estimated standard deviation in the time for activity E?