Day: Mon. Tue. Wed. Thur. Fri. Sat. Sun.
Minimum employees required: 9 2 8 6 9 1 3
If there are no day offs provided on Thursday and Friday, the number of employees required to work on Thursday as per
the final employee schedule is _____.
a. 9
b. 10
c. 11
d. 12
18. In the context of sequencing, _____ is the difference between the completion time and the due date of a job.
a. flow time
b. makespan
c. lateness
d. tardiness
19. Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due
date of completion is provided in the following table.
Job Processing Time (days) Due Date
A 6 18
B 3 14
C 4 9
D 5 19
E 2 11
Using the earliest due date (EDD) rule, the average flow time for the five jobs is _____.
a. more than 8 but less than or equal to 10 days.
b. more than 10 but less than or equal to 12 days.
c. more than 12 but less than or equal to 14 days.
d. more than 14 but less than or equal to 16 days.
20. In the context of sequencing, the earliest due date (EDD) rule:
a. minimizes the maximum jobs past due.
b. maximizes average flow time of jobs past due.
c. maximizes resource utilization of jobs past due.
d. minimizes the average processing time of jobs past due.
21. In the context of operations management, _____ refers to the assignment of start and completion times to particular
jobs, people, or equipment.
a. scheduling
b. appointing
c. statistical forecasting
d. demand planning
22. Albert’s Printing and Pressing Company is a t-shirt printing shop with four processes: printing (P1), pressing (P2),
sealing (S), and finishing (F). The arrival time and processing sequence for three upcoming jobs is shown below.
Job Arrival Time Processing Sequence (Processing Time in minutes)
1 0 P1(10), P2(20), S(15), F(10)
2 10 P1(10), P2(10), S(15)
3 20 P1(20), S(5), F(10)