Chapter 13 – Project Scheduling
d. EF = ES.
37. For an activity with more than one immediate successor activity, its latest-finish time is equal to the
a. largest latest-finish time among its immediate successors.
b. smallest latest-finish time among its immediate successors.
c. largest latest-start time among its immediate successors.
d. smallest latest-start time among its immediate successors.
38. Which of the following is a general rule for crashing activities?
a. Crash only non-critical activities.
b. Crash activities with zero slack.
c. Crash activities with the greatest number of predecessors.
d. Crash the path with the fewest activities.
39. To calculate an activity’s latest finish time, you should consider its
a. predecessors’ latest finish times
b. predecessors’ latest start times
c. successors’ earliest start times
d. successors’ latest start times
40. A critical activity is
a. an activity that consumes no time but shows precedence between events.
b. a milestone accomplishment within the project.
c. an activity with zero slack.
d. the beginning of an event.
41. The main difference between CPM and PERT is
a. the use of different activity time estimates.
b. PERT analysis is less expensive to conduct.
c. PERT lends itself to computerization while CPM networks must be constructed manually.
d. CPM integrates time and cost performance while PERT is based solely on time performance.