105) An alternative approach to project crashing is to use which of the following techniques?
A) linear programming
B) nonlinear programming
C) Markov analysis
D) queuing theory
E) None of the above
106) Which of the following is not a decision variable when formulating the project crashing problem as a linear
program?
A) the early finish times of critical activities
B) the early finish times of non critical activities
C) the start time of the project
D) the finish time of the project
E) the early start times of all activities
107) Which of the following statement about project crashing is false?
A) The crash cost is greater than or equal to the normal cost of an activity.
B) The crash time is less than or equal to the normal time to complete an activity.
C) Reducing the time of an activity on the critical path automatically reduces total project duration.
D) It may not be possible to crash a particular activity.
E) Crashing may not lead to an overall reduction in costs for the project.
108) The process of smoothing out the utilization of resources in a project is called
A) CPM.
B) PERT.
C) project crashing.
D) work breakdown structure.
E) resource leveling.