Management Chapter 12 1 Gantt charts contain information about the time taken by each activity, but not about the sequential dependencies of the activities.

subject Type Homework Help
subject Pages 12
subject Words 2938
subject Authors Barry Render, Jr. Ralph M. Stair, Michael E. Hanna

Unlock document.

This document is partially blurred.
Unlock all pages and 1 million more documents.
Get Access
page-pf1
Quantitative Analysis for Management, 11e (Render)
Chapter 12 Project Management
1) PERT and CPM are quantitative analysis tools designed to schedule and control large projects.
2) PERT is a deterministic analysis tool allowing for precise times of activities within a project.
3) PERT had its beginnings in a military department of the United States.
4) CPM is a probabilistic analysis of managing a project.
5) The first step in planning and scheduling a project is to develop the work breakdown structure.
6) A PERT/CPM network is a graphical display of a project that connects activities.
7) The optimistic time is the greatest amount of time that could be required to complete an activity.
8) PERT is a network technique similar to CPM, but PERT allows for project crashing, whereas CPM does not.
9) In PERT, the most likely completion time of an activity is used to represent that activity's time within a project.
page-pf2
10) The expected completion time and variance of an activity is approximated by the normal distribution in a
PERT analysis.
11) PERT was developed for a project for which activity or task times were uncertain.
12) CPM was developed for use in managing projects about which we have good information about activity or
task completion times.
13) With PERT, we are able to calculate the probability of finishing the project within a specified time.
14) With CPM, we are able to calculate the probability of finishing the project within a specified time.
15) Both PERT and CPM networks show activities and activity sequences.
16) The identification of the project activities and their time, cost, resource requirements, predecessors, and
person(s) responsible is called PERT planning.
17) Before drawing a PERT or CPM network, we must identify all activities and their predecessors.
18) The three time estimates employed in PERT are optimistic time, average time, and pessimistic time.
page-pf3
19) Given the variability of the activity completion times, the original critical path we identify in our PERT
analysis may not always be the actual critical path as the project takes place.
20) In PERT, the earliest start time for an activity is equal to the latest of the earliest finish times of all of its
immediate predecessors.
21) PERT stands for Probabilistic Evaluation and Review Technique.
22) One of the most significant benefits of PERT is that it forces the project manager to sit down and plan the
project in great detailand thus come to an understanding of relationships between the activities.
23) Slack is the time an activity can be delayed without impacting the completion time of the project.
24) The variance of the project completion time is equal to the sum of the variances of all the activities.
25) In PERT, we assume that the project completion time can be modeled by the normal distribution.
26) One PERT/COST assumption is that money is spent at a constant rate over the time taken to complete an
activity.
27) CPM stands for Comprehensive Project Method.
page-pf4
28) The longest time path through a PERT/CPM network is called the critical path.
29) In CPM, crashing an activity that is not on the critical path increases the cost of the project.
30) Through the use of PERT/CPM, astute managers can derive flexibility by identifying noncritical activities and
replanning, rescheduling, and reallocating resources such as personnel and finances.
31) In PERT, the variance in completion time is equal to the variance of the most time consuming activity on the
critical path.
32) Given the assumptions in PERT, the probability that a project will be completed in less time than required by
the activities on the critical path is approximately 50%.
33) Gantt charts and PERT diagrams provide the same information, just in different formats.
34) Gantt charts contain information about the time taken by each activity, but not about the sequential
dependencies of the activities.
35) The critical path of a network is the
A) shortest time path through the network.
B) path with the fewest activities.
C) path with the most activities.
D) longest time path through the network.
E) None of the above
page-pf5
36) In a PERT network, the earliest (activity) start time is the
A) earliest time that an activity can be finished without delaying the entire project.
B) latest time that an activity can be started without delaying the entire project.
C) earliest time that an activity can start without violation of precedence requirements.
D) latest time that an activity can be finished without delaying the entire project.
E) None of the above
37) Slack time in a network is the
A) amount of time that an activity would take assuming very unfavorable conditions.
B) shortest amount of time that could be required to complete the activity.
C) amount of time that you would expect it would take to complete the activity.
D) difference between the expected completion time of the project using pessimistic times and the expected
completion time of the project using optimistic times.
E) amount of time that an activity can be delayed without delaying the entire project.
38) The first step in planning and scheduling a project is to develop the ________.
A) employee scheduling plan
B) PERT/CPM network diagram
C) critical path
D) work breakdown structure
E) variance calculations for each activity
39) Which of the following is not a concept associated with CPM?
A) normal time
B) probability
C) normal cost
D) crash cost
E) deterministic network
40) PERT
A) assumes that we do not know ahead of time what activities must be completed.
B) assumes that activity time estimates follow the normal probability distribution.
C) is a network technique that uses three time estimates for each activity in a project.
D) is a deterministic network technique that allows for project crashing.
E) None of the above
page-pf6
41) CPM
A) assumes we do not know ahead of time what activities must be completed.
B) assumes that activity time estimates follow the normal probability distribution.
C) is a deterministic network technique that allows for project crashing.
D) is a network technique that allows three time estimates for each activity in a project.
E) None of the above
42) Managers use the network analysis of PERT and CPM to help them
A) derive flexibility by identifying noncritical activities.
B) replan, reschedule, and reallocate resources such as manpower and finances.
C) plan, schedule, monitor, and control large and complex projects.
D) All of the above
E) None of the above
43) The expected time in PERT is
A) a weighted average of the most optimistic time, most pessimistic time, and four times the most likely time.
B) the modal time of a beta distribution.
C) a simple average of the most optimistic, most likely, and most pessimistic times.
D) the square root of the sum of the variances of the activities on the critical path.
E) None of the above
44) Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 6, and 14 days respectively,
compute the PERT expected activity time for this activity.
A) 8
B) 6
C) 7
D) 9
E) None of the above
page-pf7
45) Given an activity's optimistic, most likely, and pessimistic time estimates of 2, 5, and 14 days respectively,
compute the PERT expected activity time for this activity.
A) 6
B) 7
C) 9
D) 5
E) None of the above
46) Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 14, and 18 days respectively,
compute the PERT expected activity time for this activity.
A) 14
B) 12
C) 11
D) 13
E) None of the above
47) Given an activity's optimistic, most likely, and pessimistic time estimates of 2, 10, and 20 days respectively,
compute the PERT variance for this activity.
A) 3
B) 6
C) 9
D) 18
E) None of the above
48) Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 12, and 18 days respectively,
compute the PERT variance for this activity.
A) 2.33
B) 5.44
C) 8.00
D) 64.00
E) None of the above
page-pf8
49) Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 5, and 15 days, respectively,
compute the PERT standard deviation for this activity.
A) 2
B) 4
C) 5
D) 15
E) None of the above
50) Given the following small project, the critical path is ________ days.
Activity
Immediate
Predecessor
Time
(days)
A
-
10
B
-
4
C
A, B
6
A) 10
B) 14
C) 16
D) 20
E) None of the above
51) Given the following small project, the critical path is ________ days.
Activity
Immediate
Predecessor
Time
(days)
A
-
8
B
A
4
C
-
10
A) 4
B) 10
C) 12
D) 22
E) None of the above
page-pf9
Table 12-1
The following represents a project with know activity times. All times are in weeks.
Immediate
Predecessor
Time
-
4
-
3
A
2
B
7
C, D
4
B
5
52) Using the data in Table 12-1, what is the minimum possible time required for completing the project?
A) 8
B) 14
C) 25
D) 10
E) None of the above
53) Using the data in Table 12-1, what is the latest possible time that C may be started without delaying
completion of the project?
A) 0
B) 4
C) 8
D) 10
E) None of the above
54) According to Table 12-1, compute the slack time for activity D.
A) 0
B) 5
C) 3
D) 6
E) None of the above
page-pfa
55) Using the data in Table 12-1, compute the latest finish time for activity E.
A) 4
B) 10
C) 14
D) 25
E) None of the above
Table 12-2
The following represents a project with four activities. All times are in weeks.
Activity
Immediate
Predecessor
Optimistic
Time
Most
Likely
Time
Pessimistic
Time
A
-
2
8
14
B
-
8
8
8
C
A
6
9
18
D
B
5
11
17
56) According to the data in Table 12-2, what is the critical path?
A) A-B
B) A-C
C) B-D
D) A-B-C-D
E) None of the above
57) According to the data in Table 12-2, what is the minimum expected completion time for the project?
A) 18
B) 19
C) 37
D) 11
E) None of the above
page-pfb
58) According to Table 12-2, there are four activities in the project. Assume the normal distribution is appropriate
to use to determine the probability of finishing by a particular time. If you wished to find the probability of
finishing the project in 20 weeks or fewer, it would be necessary to find the variance and then the standard
deviation to be used with the normal distribution. What variance would be used?
A) 2
B) 4
C) 8
D) 12
E) None of the above
59) According to Table 12-2, there are four activities in the project. Assume the normal distribution is appropriate
to use to determine the probability of finishing by a particular time. What is the probability that the project is
finished in 16 weeks or fewer? (Round to two decimals.)
A) 0.07
B) 0.93
C) 0.43
D) 0.77
E) None of the above
60) Consider a project that has an expected completion time of 60 weeks and a standard deviation of five weeks.
What is the probability that the project is finished in 70 weeks or fewer? (Round to two decimals.)
A) 0.98
B) 0.48
C) 0.50
D) 0.02
E) 0.63
page-pfc
61) Your company is considering submitting a bid on a major project. You determine that the expected
completion time is 100 weeks and the standard deviation is 10 weeks. It is assumed that the normal distribution
applies. You wish to set the due date for the project such that there is an 85 percent chance that the project will be
finished by this time. What due date should be set?
A) 108.0
B) 110.4
C) 89.6
D) 85.0
E) 100
Table 12-3
Activity
Immediate
Predecessor
Optimistic
Most
Likely
Pessimistic
Standard
Deviation
Variance
A
--
4
5
6
0.333
0.111
B
--
12
16
18
1.000
1.000
C
A
2
8
14
2.000
4.000
D
A
5
5
5
0.000
0.000
E
B, C
6
7
8
0.333
0.111
62) According to Table 12-3, there are five activities in a PERT project. Which activities are on the critical path?
A) A-B-C-D-E
B) A-C-E
C) B-D
D) A-B-C-D
E) B-E
63) According to Table 12-3, there are five activities in a PERT project. What is the variance of the critical path?
A) 5.222
B) 4.222
C) 1.222
D) 0
E) 1.111
page-pfd
64) According to Table 12-3, there are five activities in a PERT project. If the normal distribution were used to
find the probability of finishing this project in 24 weeks or fewer, what mean and variance would be used?
A) 20 and 4.222
B) 30 and 5.222
C) 20 and 5.222
D) 30 and 4.222
E) 22.667 and 1.111
65) The critical path of a network is the
A) path with the least variance.
B) path with zero slack.
C) path with the most activities.
D) path with the largest variance.
E) None of the above
66) In a PERT network, the latest (activity) start time is the
A) earliest time that an activity can be finished without delaying the entire project.
B) latest time that an activity can be started without delaying the entire project.
C) earliest time that an activity can start without violation of precedence requirements.
D) latest time that an activity can be finished without delaying the entire project.
E) None of the above
67) The work breakdown structure involves identifying the ________ for each activity.
A) time
B) cost
C) resource requirements
D) predecessors
E) All of the above
page-pfe
68) PERT stands for ________.
A) probabilistic evaluation and review technique
B) program evaluation and review technique
C) probability of expected run times
D) program of expected run times
E) project evaluation and review technique
69) CPM stands for ________.
A) critical path management
B) critical project management
C) critical project method
D) critical path method
E) centralized project management
70) Which of the following questions can be answered by PERT?
A) When will the entire project be completed?
B) What is the probability that the project will be completed by a specific date?
C) What are the critical activities?
D) What are the noncritical activities?
E) All of the above
71) In PERT, we assume that
A) the times to complete individual activities are known with certainty.
B) all activities are carried out by staff from our own organization.
C) the total cost of a project is independent of the time to complete the project.
D) the total time to complete all activities on the critical path is described by a normal distribution.
E) None of the above
72) The two common techniques for drawing PERT networks are ________.
A) NOA and NRA
B) AON and AOA
C) GANTT and NOA
D) ONA and OAO
E) CAN and CAA
page-pff
73) In PERT analysis, the probability of the optimistic time occurring should be on the order of ________.
A) 1/2
B) 1/3
C) 1/6
D) 1/10
E) 1/100
74) The expected time in PERT is
A) greater than the most likely time.
B) equal to the most likely time.
C) less than the most likely time.
D) any of the above
E) None of the above
75) Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 7, and 11 days respectively,
compute the expected time for this activity.
A) 5
B) 6
C) 7
D) 12
E) None of the above
76) Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 5, and 13 days respectively,
compute the expected time for this activity.
A) 3
B) 4
C) 5
D) 6
E) None of the above
page-pf10
77) Given an activity's optimistic, most likely, and pessimistic time estimates of 1, 9, and 23 days respectively,
compute the PERT expected activity time for this activity.
A) 10
B) 12
C) 9
D) 11
E) None of the above
78) Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 6, and 9 days respectively,
compute the PERT variance for this activity.
A) 3
B) 1
C) 9
D) 6
E) None of the above
page-pf11
79) The project described by:
Activity
Immediate
Predecessor
Time
(days)
A
--
10
B
A
4
C
A
6
D
B
7
E
C
5
is best represented by which of the following networks?
A)
B)
C)
D)
E) None of the above
page-pf12
80) The project described by:
Activity
Immediate
Predecessor
Time
(days)
A
--
10
B
A
4
C
A
6
D
B, C
7
E
C
5
has a critical path of length of ________.
A) 21 days
B) 14 days
C) 23 days
D) 32 days
E) None of the above
81) The project described by:
Activity
Immediate
Predecessor
Time
(days)
A
--
6
B
A
2
C
--
8
D
B, C
5
E
D
7
has a critical path of length of ________.
A) 15 days
B) 20 days
C) 17 days
D) 18 days
E) None of the above

Trusted by Thousands of
Students

Here are what students say about us.

Copyright ©2022 All rights reserved. | CoursePaper is not sponsored or endorsed by any college or university.