Which of the following is not one of the network rules for PERT/CPM?
a. Networks start and finish at multiple events.
b. Identify each unique activity within a project by a capital letter that corresponds only
to that activity.
c. Branch direction indicates the general progression in time from left to right.
d. When a number of activities end at one event, no activity starting at that event may
begin before all activities ending at that event are complete.
e. Two or more activities cannot share graphically the same beginning and ending
events.
All of the following are elements of market risk in a supply base except _____.
a. the number of buyers competing for the same goods or source of supply
b. increasingly shorter product life cycles
c. regional political risk
d. threat of emerging, often disruptive, technologies
e. protecting and maintaining trade secrets and intellectual properties from misuse or
misappropriation by suppliers, particularly those located overseas
A/An _____ is an integrated collection of computer files capable of storing operational
data essential for managing a department.