11. Ashgate Enterprises uses the NPV method for selecting projects, and it does a reasonably good job of estimating
projects’ sales and costs. However, it never considers real options that might be associated with projects. Which of the
following statements is most likely to describe its situation?
a. Its estimated capital budget is probably too large due to its failure to consider abandonment and growth options.
b. Failing to consider abandonment and flexibility options probably makes the optimal capital budget too large, but
failing to consider growth and timing options probably makes the optimal capital budget too small, so it is unclear what
impact not considering real options has on the overall capital budget.
c. Failing to consider abandonment and flexibility options probably makes the optimal capital budget too small, but
failing to consider growth and timing options probably makes the optimal capital budget too large, so it is unclear what
impact not considering real options has on the overall capital budget.
d. Real options should not have any effect on the size of the optimal capital budget.
e. Its estimated capital budget is probably too small, because projects’ NPVs are often larger when real options are
taken into account.
Drilling Experts, Inc.
Drilling Experts, Inc. (DEI) finds and develops oil properties and then sells the successful ones to major oil refining
companies. DEI is now considering a new potential field, and its geologists have developed the following data, in
thousands of dollars.
t = 0. A $400 feasibility study would be conducted at t = 0. The results of this study would determine if the company
should commence drilling operations or make no further investment and abandon the project.
t = 1. If the feasibility study indicates good potential, the firm would spend $1,000 at t = 1 to drill exploratory wells.
The best estimate is that there is an 80% probability that the exploratory wells would indicate good potential and thus that
further work would be done, and a 20% probability that the outlook would look bad and the project would be abandoned.