Page 406 Conceptual M/C Chapter 11: Capital Budgeting
59. Which of the following statements is CORRECT?
a. The NPV, IRR, MIRR, and discounted payback (using a payback
requirement of 3 years or less) methods always lead to the same
accept/reject decisions for independent projects.
b. For mutually exclusive projects with normal cash flows, the NPV and
MIRR methods can never conflict, but their results could conflict
with the discounted payback and the regular IRR methods.
c. Multiple IRRs can exist, but not multiple MIRRs. This is one reason
some people favor the MIRR over the regular IRR.
d. If a firm uses the discounted payback method with a required payback
of 4 years, then it will accept more projects than if it used a
regular payback of 4 years.
e. The percentage difference between the MIRR and the IRR is equal to
the project’s WACC.
60. Which of the following statements is CORRECT?
a. For a project with normal cash flows, any change in the WACC will
change both the NPV and the IRR.
b. To find the MIRR, we first compound cash flows at the regular IRR to
find the TV, and then we discount the TV at the WACC to find the PV.
c. The NPV and IRR methods both assume that cash flows can be
reinvested at the WACC. However, the MIRR method assumes
reinvestment at the MIRR itself.
d. If two projects have the same cost, and if their NPV profiles cross
in the upper right quadrant, then the project with the higher IRR
probably has more of its cash flows coming in the later years.
e. If two projects have the same cost, and if their NPV profiles cross
in the upper right quadrant, then the project with the lower IRR
probably has more of its cash flows coming in the later years.
61. Which of the following statements is CORRECT?
a. One advantage of the NPV over the IRR is that NPV takes account of
cash flows over a project’s full life whereas IRR does not.
b. One advantage of the NPV over the IRR is that NPV assumes that cash
flows will be reinvested at the WACC, whereas IRR assumes that cash
flows are reinvested at the IRR. The NPV assumption is generally
more appropriate.
c. One advantage of the NPV over the MIRR method is that NPV takes
account of cash flows over a project’s full life whereas MIRR does
not.
d. One advantage of the NPV over the MIRR method is that NPV discounts
cash flows whereas the MIRR is based on undiscounted cash flows.
e. Since cash flows under the IRR and MIRR are both discounted at the
same rate (the WACC), these two methods always rank mutually
exclusive projects in the same order.