32) Which of the following is NOT one of the steps taken in the financial planning
process?
a.Monitor operations after implementing the plan to spot any deviations and then take
corrective actions
b.Determine the amount of capital that will be needed to support the plan
c.Develop a set of forecasted financial statements under alternative versions of the
operating plan in order to analyze the effects of different operating procedures on
projected profits and financial ratios
d.Consult with key competitors about the optimal set of prices to charge, i.e., the prices
that will maximize profits for our firm and its competitors
e.Forecast the funds that will be generated internally. If internal funds are insufficient to
cover the required new investment, then identify sources from which the required
external capital can be raised
33) In Japan, 90-day securities have a 4% annualized return and 180-day securities have
a 5% annualized return. In the United States, 90-day securities have a 4% annualized
return and 180-day securities have an annualized return of 4.5%. All securities are of
equal risk, and Japanese securities are denominated in terms of the Japanese yen.
Assuming that interest rate parity holds in all markets, which of the following
statements is most CORRECT?
a.The yen-dollar spot exchange rate equals the yen-dollar exchange rate in the 180-day
forward market
b.The yen-dollar exchange rate in the 90-day forward market equals the yen-dollar
exchange rate in the 180-day forward market
c.The spot rate equals the 90-day forward rate
d.The spot rate equals the 180-day forward rate
e.The yen-dollar spot exchange rate equals the yen-dollar exchange rate in the 90-day
forward market
34) Which of the following statements is CORRECT? Assume that the project being
considered has normal cash flows, with one outflow followed by a series of inflows.
a.The lower the WACC used to calculate a project’s NPV, the lower the calculated NPV
will be
b.If a project’s NPV is less than zero, then its IRR must be less than the WACC
c.If a project’s NPV is greater than zero, then its IRR must be less than zero
d.The NPV of a relatively low-risk project should be found using a relatively high