Which of the following production process terms best describes the situation when
activities in a stage of production must stop because there is no work?
A. Blocking
B. Buffering
C. Starving
D. Buffer
E. Setup time
Here are the data for a time-cost CPM scheduling analysis. The time is in days and the
costs include both direct and indirect costs.
If you crash this project to reduce the total time by four days, what is the total time of
the project and total cost?
A. Total time is 10 days, total cost is $2,500.
B. Total time is 9 days, total cost is $2,300.
C. Total time is 8 days, total cost is $2,750.
D. Total time is 8 days, total cost is $1,850.