Assume there are five jobs (i.e., A, B, C, D, and E) that need to be sequenced in a
production schedule. The remaining operating time necessary for completion of job A is
3 days (i.e., job A will take 3 more days to complete), B will take 9 days, C will take 6
days, D will take 5 days and E will take 8 days. In what order will these jobs be
scheduled if using the SOT priority rule for job sequencing?
A. A-B-D-E-C
B. A-D-C-E-B
C. D-C-A-B-E
D. B-E-C-D-A
E. E-D-A-B-C
For an activity in a CPM analysis, the early start time is 8 and the late start time is 10.
Which of the following statements is true?
A. The late finish is 12.
B. The early finish is 10.
C. The slack for this activity is 2.
D. The duration of this activity is 2.
E. The activity is on the critical path.