71.
A company is choosing between two projects. The larger project has an initial cost of $100,000, annual cash
flows
of $30,000 for 5 years, and an IRR of 15.24%. The smaller project has an initial cost of $51,600, annual
cash flows
of $16,000 for 5 years, and an IRR of 16.65%. The projects are equally risky. Which of the
following statements is
CORRECT?
a.
Since the smaller project has the higher IRR, the two projects’ NPV profiles cannot cross, and the smaller
project’s NPV will be higher at all positive values of WACC.
b.
Since the smaller project has the higher IRR, the two projects’ NPV profiles will cross, and the larger
project
will look better based on the NPV at all positive values of WACC.
c.
If the company uses the NPV method, it will tend to favor smaller, shorter-term projects over larger,
longer-
term projects, regardless of how high or low the WACC is.
d.
Since the smaller project has the higher IRR but the larger project has the higher NPV at a zero discount
rate, the two projects’ NPV profiles will cross, and the larger project will have the higher NPV if the
WACC
is less than the crossover rate.
e.
Since the smaller project has the higher IRR and the larger NPV at a zero discount rate, the two projects’
NPV profiles will cross, and the smaller project will look better if the WACC is less than the crossover
rate.
72.
McCall Manufacturing has a WACC of 10%. The firm is considering two normal, equally risky, mutually
exclusive,
but not repeatable projects. The two projects have the same investment costs, but Project A has an
IRR of 15%,
while Project B has an IRR of 20%. Assuming the projects’ NPV profiles cross in the upper
right quadrant, which
of the following statements is CORRECT?
a.
Each project must have a negative NPV.
b.
Since the projects are mutually exclusive, the firm should always select Project B.
c.
If the crossover rate is 8%, Project B will have the higher NPV.
d.
Only one project has a positive NPV.
e.
If the crossover rate is 8%, Project A will have the higher NPV.