Chapter 7: Project Cost Management
c.
rough order of magnitude
d.
ballpark
Budgetary estimates are made one to two years prior to project completion.
1
Difficulty: Easy
p.272
INFO.SCHW.14.51 – LO: 7-4
United States – BUSPROG: Technology
Estimating Costs
Bloom’s: Knowledge
a.
budgetary
b.
definitive
c.
rough order of magnitude
d.
final
b
1
Difficulty: Easy
p.272
INFO.SCHW.14.51 – LO: 7-4
United States – BUSPROG: Technology
Estimating Costs
Bloom’s: Knowledge
a.
Definitive estimates
b.
Parametric estimates
c.
Bottom-up estimates
d.
Analogous estimates
d
judgment and is generally less costly than other techniques, but it is also less accurate.
1
Difficulty: Easy
p.273
INFO.SCHW.14.51 – LO: 7-4
United States – BUSPROG: Technology
Estimating Costs
Bloom’s: Knowledge
Chapter 7: Project Cost Management
a.
bottom-up
b.
top-down
c.
parametric
d.
budgetary
b
for estimating the cost of the current project. They are also called top-down estimates.
1
Difficulty: Easy
p.273
INFO.SCHW.14.51 – LO: 7-4
United States – BUSPROG: Technology
Estimating Costs
Bloom’s: Knowledge
a.
Their main disadvantage is that they cost more than other techniques.
b.
They are the only technique which do not require expert judgement.
c.
They are most reliable when previous projects are similar in fact with current projects.
d.
They use project characteristics in a mathematical model to estimate project costs.
1
p.273
INFO.SCHW.14.51 – LO: 7-4
United States – BUSPROG: Technology
Estimating Costs
Bloom’s: Comprehension
a.
budgetary
b.
parametric
c.
bottom-up
d.
analogous
1
Difficulty: Easy
p.274
INFO.SCHW.14.51 – LO: 7-4
United States – BUSPROG: Technology
Bloom’s: Knowledge
a.
They are based on the actual cost of a previous, similar project.
b.
They are also known as parametric estimating.
c.
They are most accurate when they involve large, extensive work items.
d.
They are time-intensive and expensive to develop.
Difficulty: Moderate
INFO.SCHW.14.51 – LO: 7-4
United States – BUSPROG: Technology
Estimating Costs
Bloom’s: Comprehension
a.
Rough order of magnitude estimating
b.
Parametric estimating
c.
Bottom-up estimating
d.
Analogous estimating
model to estimate project costs.
Difficulty: Knowledge
INFO.SCHW.14.51 – LO: 7-4
United States – BUSPROG: Technology
Estimating Costs
Bloom’s: Knowledge
a.
Estimates take a long time to be worked out.
b.
People lack estimating experience.
c.
Human beings are biased toward overestimation.
d.
Only software development provides the scope for estimates to be accurate.
a.
budgetary
b.
definitive
c.
rough order of magnitude
d.
analogous
reporting, it should be a definitive estimate and as accurate as possible.
1
Difficulty: Moderate
p.276
INFO.SCHW.14.51 – LO: 7-4
United States – BUSPROG: Technology
Estimating Costs
Bloom’s: Comprehension
a.
cost budgeting
b.
cost planning
c.
cost controlling
d.
cost estimating
Difficulty: Moderate
p.281
INFO.SCHW.14.52 – LO: 7-5
United States – BUSPROG: Analytic
Determining the Budget
Bloom’s: Comprehension
a.
Cost forecasts
b.
Project funding requirements
c.
Basis of estimates
d.
Scope baselines
organizational process asset updates.
1
United States – BUSPROG: Technology
Estimating Costs
Bloom’s: Comprehension
a.
Cost forecasts
b.
Work performance data
c.
Change requests
d.
Scope baseline
Difficulty: Moderate
INFO.SCHW.14.53 – LO: 7-6
United States – BUSPROG: Technology
Controlling Costs
Bloom’s: Knowledge
a.
earned value
b.
actual cost
c.
indirect cost
d.
planned value
cost estimate planned to be spent on an activity during a given period.
Difficulty: Easy
INFO.SCHW.14.53 – LO: 7-6
United States – BUSPROG: Technology
Controlling Costs
Bloom’s: Knowledge
a.
It is the actual cost plus the planned cost.
b.
It is based solely on the total cost estimate to be spent on an activity.
c.
It is an estimate of the value of the physical work actually completed.
d.
It is also known as the planned value.
INFO.SCHW.14.53 – LO: 7-6
United States – BUSPROG: Technology
Controlling Costs
Bloom’s: Comprehension
a.
earned value
b.
schedule variance
c.
planned value
d.
rate of performance
Difficulty: Moderate
INFO.SCHW.14.53 – LO: 7-6
United States – BUSPROG: Analytic
Controlling Costs
Bloom’s: Comprehension
a.
the planned value plus actual costs.
b.
the earned value minus the actual cost.
c.
the rate of performance minus earned value.
d.
the planned value minus the rate of performance.
Difficulty: Moderate
INFO.SCHW.14.53 – LO: 7-6
United States – BUSPROG: Analytic
Controlling Costs
Bloom’s: Comprehension
a.
the earned value minus the planned value.
b.
the earned value minus the actual cost.
c.
the planned value plus the earned value.
d.
the planned value plus the rate of performance.
INFO.SCHW.14.53 – LO: 7-6
United States – BUSPROG: Technology
Controlling Costs
Bloom’s: Comprehension
a.
indicates that a project is under budget if CPI is less than one.
b.
can be used to estimate the projected cost of completing the project.
c.
indicates that the planned and actual costs are equal if CPI is more than one.
d.
is the ratio of earned value to planned value.
Difficulty: Moderate
INFO.SCHW.14.53 – LO: 7-6
United States – BUSPROG: Technology
Controlling Costs
Bloom’s: Comprehension
a.
It can be used to estimate the projected time to complete the project.
b.
It means that a project is behind schedule if an SPI is greater than one.
c.
It means that a project is ahead of schedule if SPI is lesser than one or hundred percent.
d.
It is the ratio of planned value to actual costs.
value; it can be used to estimate the projected time to complete the project.
Difficulty: Moderate
INFO.SCHW.14.53 – LO: 7-6
United States – BUSPROG: Technology
Controlling Costs
Bloom’s: Comprehension
Difficulty: Moderate
INFO.SCHW.14.53 – LO: 7-6
United States – BUSPROG: Analytic
Controlling Costs
Bloom’s: Comprehension
Chapter 7: Project Cost Management
learning curve
Difficulty: Moderate
United States – BUSPROG: Technology
Bloom’s: Comprehension
INFO.SCHW.14.50 – LO: 7-3
Planning Cost Management
rough order of magnitude (ROM)
Difficulty: Easy
INFO.SCHW.14.51 – LO: 7-4
United States – BUSPROG: Technology
Bloom’s: Knowledge
rough order of magnitude (ROM)
United States – BUSPROG: Technology
Estimating Costs
Bloom’s: Knowledge
Chapter 7: Project Cost Management
INFO.SCHW.14.53 – LO: 7-6
Controlling Costs
INFO.SCHW.14.53 – LO: 7-6
Controlling Costs
INFO.SCHW.14.53 – LO: 7-6
Controlling Costs
schedule performance
Difficulty: Easy
INFO.SCHW.14.53 – LO: 7-6
United States – BUSPROG: Technology
Bloom’s: Knowledge
Bloom’s: Comprehension
Chapter 7: Project Cost Management