16) Which of the following statements about the project budgeting process is TRUE?
A) The weekly budget is formed by only using the early start times of each activity.
B) The weekly budget is formed by only using the late start times of each activity.
C) The weekly budget is formed by only using the early start time of each activity on the critical path.
D) The weekly budget is formed by using both the early start and finish times of each activity on the
critical path.
E) The weekly budget is formed by using both the early start and finish times of each activity.
17) A graph that plots the total resources needed per period vs. time is called a(n) ________.
A) Gantt Chart
B) Resource Loading Chart
C) Work Breakdown Structure
D) Project Network Chart
E) PERT/CPM Chart
18) Activity A has a standard cost of $500 and the standard time to complete Activity A is 5 weeks. The
crash time for Activity A is 3 weeks and the crash cost is $600. What is the crash cost per week for
Activity A?
A) $50
B) $100
C) $150
D) $200
E) $300
19) Which of the following statements about project crashing is FALSE?
A) The overall project time is reduced by crashing activities on one or more critical paths.
B) It is best to crash an activity with the cheapest cost to crash per week.
C) As activities are crashed in a project network, it is possible for more than one path to be critical.
D) In order to reduce the overall project time, it may be necessary to crash more than one activity.
E) Project crashing problems can be solved using linear programming.