Chapter 6: Resource Utilization
21. In resource-limited scheduling, the lower priority activities get delayed. How does the delaying of activities affect the
project?
a. The delaying of activities increases the costs of the project.
b. The delaying of activities decreases the acceptance of the project deliverable.
c. The delaying of activities may delay the project.
d. The delaying of activities helps give others more time on their tasks because they won’t affect the project
schedule.
22. This example has level resources of three resources for eight days. If the project is limited to two resources, how
should the project be organized to meet the resource constraint and finish the project as early as possible? The tasks
with the least slack have the lower number.
a. Paths would be 1,2,3,5 and 1,2,4
b. Paths would be 1,2,3,4 and 1,2,5
c. Paths would be 1,2 and 3,4,5
d. Path would be 1,2,3,4,5