Chapter 6: Project Time Management
True / False
1. An activity is an element of work that has an expected duration, cost, and resource requirements.
a.
True
b.
False
True
structure (WBS) that has expected duration, cost, and resource requirements.
1
Difficulty: Easy
p.223
INFO.SCHW.14.39 – LO: 6-1
The Importance of Project Schedules
Bloom’s: Knowledge
2. In project time management, the primary output of defining activities is a schedule management plan.
a.
True
b.
False
False
1
Difficulty: Moderate
p.223
INFO.SCHW.14.39 – LO: 6-1
United States – BUSPROG: Analytic
The Importance of Project Schedules
Bloom’s: Comprehension
3. In project time management, the next step after sequencing activities is to define these activities.
a.
True
b.
False
False
time management, this process follows after sequencing activities.
1
Difficulty: Easy
p.224
INFO.SCHW.14.39 – LO: 6-1
United States – BUSPROG: Analytic
The Importance of Project Schedules
Bloom’s: Knowledge
4. Project schedules grow out of basic documents such as the project charter.
a.
True
b.
False
True
1
Difficulty: Easy
p.225
INFO.SCHW.14.40 – LO: 6-2
Planning Schedule Management
Bloom’s: Knowledge
5. A schedule management plan includes information which describes the format and frequency of schedule reports
required for the project.
a.
True
b.
False
True
1
p.225
United States – BUSPROG: Analytic
Planning Schedule Management
6. To define activities, the project team should start with reviewing the schedule management plan, scope baseline,
enterprise environmental factors, and organizational processes.
a.
True
b.
False
True
1
Difficulty: Moderate
INFO.SCHW.14.41 – LO: 6-3
United States – BUSPROG: Analytic
7. It is important for the activity list and activity attributes to be in agreement with the work breakdown structure.
a.
True
b.
False
True
1
Difficulty: Easy
p.226
INFO.SCHW.14.41 – LO: 6-3
United States – BUSPROG: Analytic
Defining Activities
Bloom’s: Knowledge
8. Milestones are easy to achieve and are always achieved through one main activity.
a.
True
b.
False
False
1
Difficulty: Easy
p.226
INFO.SCHW.14.41 – LO: 6-3
United States – BUSPROG: Analytic
Defining Activities
Bloom’s: Knowledge
9. After defining project activities, the next step in project time management is developing the schedule.
a.
True
b.
False
False
sequencing them or determining their dependencies.
1
Difficulty: Moderate
INFO.SCHW.14.42 – LO: 6-4
Defining Activities
Bloom’s: Comprehension
10. A dependency pertains to the sequencing of project activities or tasks.
a.
True
b.
False
True
1
Difficulty: Moderate
p.228
INFO.SCHW.14.42 – LO: 6-4
United States – BUSPROG: Technology
Sequencing Activities
Bloom’s: Comprehension
11. Network diagrams are the preferred technique for showing activity sequencing.
a.
True
b.
False
True
1
Difficulty: Easy
p.229
INFO.SCHW.14.42 – LO: 6-4
United States – BUSPROG: Technology
Sequencing Activities
Bloom’s: Knowledge
12. The arrows in a network diagram represent missed milestones in a project.
a.
True
b.
False
False
1
Difficulty: Easy
INFO.SCHW.14.42 – LO: 6-4
Sequencing Activities
Bloom’s: Comprehension
13. In a network diagram, it is mandatory for every item on the WBS to be shown instead of only those activities with
dependencies.
a.
True
b.
False
False
1
Difficulty: Moderate
p.229
INFO.SCHW.14.42 – LO: 6-4
United States – BUSPROG: Technology
Sequencing Activities
Bloom’s: Comprehension
14. A merge occurs when one node precedes mutiple nodes.
a.
True
b.
False
False
1
Difficulty: Moderate
p.230
INFO.SCHW.14.42 – LO: 6-4
United States – BUSPROG: Technology
Sequencing Activities
Bloom’s: Comprehension
15. Start-to-finish relationships are the most frequently used dependencies between activities.
a.
True
b.
False
False
1
p.231
Sequencing Activities
Bloom’s: Knowledge
16. A drawback of the precedence diagramming method is that it cannot be used unless dummy activities are employed.
a.
True
b.
False
False
1
Difficulty: Moderate
p.232
INFO.SCHW.14.42 – LO: 6-4
United States – BUSPROG: Technology
Sequencing Activities
Bloom’s: Comprehension
17. In project time management, one should control the schedule before estimating the duration for each activity.
a.
True
b.
False
False
1
Difficulty: Moderate
p.232
INFO.SCHW.14.43 – LO: 6-5
United States – BUSPROG: Analytic
Estimating Activity Resources
Bloom’s: Comprehension
18. In a Gantt chart, thick black bars represent milestones achieved in a project.
a.
True
b.
False
False
1
p.234-235
United States – BUSPROG: Technology
Sequencing Activities
Bloom’s: Knowledge
19. A Tracking Gantt chart is based on the percentage of work completed for project tasks or the actual start and finish
dates.
a.
True
b.
False
True
1
Difficulty: Moderate
p.238
INFO.SCHW.14.44 – LO: 6-7
United States – BUSPROG: Technology
Developing the Schedule
Bloom’s: Comprehension
20. A disadvantage of using Gantt charts is that they do not provide a standard format for displaying planned project
schedule information.
a.
True
b.
False
False
for displaying planned and actual project schedule information.
1
Difficulty: Moderate
p.238
INFO.SCHW.14.44 – LO: 6-7
United States – BUSPROG: Technology
Developing the Schedule
Bloom’s: Comprehension
21. In a critical path analysis, the shortest path is what drives the completion date for the project.
a.
True
b.
False
False
Difficulty: Easy
United States – BUSPROG: Technology
Developing the Schedule
Bloom’s: Knowledge
22. The critical path on a project can change as the project progresses.
a.
True
b.
False
True
critical path on a project can change as the project progresses.
1
p.239
INFO.SCHW.14.44 – LO: 6-7
United States – BUSPROG: Technology
Developing the Schedule
Bloom’s: Knowledge
23. A backward pass through the network diagram determines the early start and early finish dates for each activity.
a.
True
b.
False
False
1
Difficulty: Easy
p.241
INFO.SCHW.14.44 – LO: 6-7
United States – BUSPROG: Technology
Developing the Schedule
Bloom’s: Knowledge
24. Knowing the amount of float allows project managers to know whether a project schedule is flexible.
a.
True
b.
False
True
Difficulty: Moderate
INFO.SCHW.14.44 – LO: 6-7
United States – BUSPROG: Technology
Developing the Schedule
Bloom’s: Knowledge
25. The main disadvantage of crashing is that it lengthens the time needed to finish a project.
a.
True
b.
False
False
project. The main disadvantage is that it often increases total project costs.
1
p.243
INFO.SCHW.14.44 – LO: 6-7
United States – BUSPROG: Technology
Developing the Schedule
Bloom’s: Comprehension
26. The technique of fast tracking can result in lengthening the project schedule.
a.
True
b.
False
True
1
Difficulty: Moderate
p.243
INFO.SCHW.14.44 – LO: 6-7
United States – BUSPROG: Technology
Developing the Schedule
Bloom’s: Comprehension
27. Critical chain scheduling assumes that resources multitask and maximizes multitasking.
a.
True
b.
False
False
1
Difficulty: Moderate
INFO.SCHW.14.44 – LO: 6-7
INFO.SCHW.14.44 – LO: 6-7
United States – BUSPROG: Technology
Developing the Schedule
Bloom’s: Comprehension
28. One of PERT’s main disadvantages is that it does not address the risk associated with duration estimates.
a.
True
b.
False
False
1
Difficulty: Moderate
p.248
INFO.SCHW.14.44 – LO: 6-7
United States – BUSPROG: Technology
Developing the Schedule
Bloom’s: Comprehension
29. The final process in project time management is developing the schedule.
a.
True
b.
False
False
1
Difficulty: Easy
p.248
INFO.SCHW.14.45 – LO: 6-8
United States – BUSPROG: Technology
Controlling the Schedule
Bloom’s: Comprehension
30. A drawback of the project management software is that it does not have the capacity to calculate the critical path(s) for
a project.
a.
True
b.
False
False
1
p.250
Developing the Schedule
Bloom’s: Comprehension
31. The first process involved in project time management is _____ .
a.
b.
estimating activity durations
c.
d.
sequencing activities
Difficulty: Easy
INFO.SCHW.14.39 – LO: 6-1
United States – BUSPROG: Analytic
The Importance Of Project Schedules
Bloom’s: Knowledge
32. Which of the following processes in project time management involves identifying the specific tasks that the project
team members and stakeholders must perform to produce the project deliverables?
a.
Defining activities
b.
Sequencing activities
c.
Developing the schedule
d.
Estimating activity durations
Difficulty: Easy
INFO.SCHW.14.39 – LO: 6-1
United States – BUSPROG: Analytic
The Importance Of Project Schedules
Bloom’s: Knowledge
33. In project time management, which of the following processes generate the main outputs of an activity list, activity
attributes, and a milestone list?
a.
Sequencing activities
b.
Defining activities
c.
Resource estimating activities
d.
Estimating activity durations
United States – BUSPROG: Technology
Using Software to Assist in Project Time Management
Bloom’s: Knowledge
Multiple Choice
34. In project time management, which of the following processes primarily involve identifying and documenting the
relationships between project activities?
a.
Defining activities
b.
Sequencing activities
c.
Planning schedule management
d.
Estimating activity durations
diagrams and project documents updates.
Difficulty: Easy
United States – BUSPROG: Analytic
The Importance Of Project Schedules
Bloom’s: Knowledge
35. In project time management, which of the following processes involve calculating the number of work periods that are
needed to complete individual activities?
a.
Defining activities
b.
Sequencing activities
c.
Planning schedule management
d.
Estimating activity durations
Difficulty: Moderate
INFO.SCHW.14.39 – LO: 6-1
United States – BUSPROG: Analytic
The Importance Of Project Schedules
Bloom’s: Comprehension
36. In project time management, which of the following processes involve analyzing activity sequences, activity resource
estimates, and activity duration estimates to create the project schedule?
a.
Planning schedule management
b.
Developing the schedule
c.
Controlling the schedule
d.
Defining activities
schedule baseline, project schedule, schedule data, project calendars, project management
INFO.SCHW.14.39 – LO: 6-1
United States – BUSPROG: Analytic
The Importance Of Project Schedules
Bloom’s: Knowledge
37. In project time management, the process of_____ primarily involves checking and managing changes to the project
schedule.
a.
estimating activity durations
b.
developing the schedule
c.
controlling the schedule
d.
estimating activity resources
Difficulty: Moderate
INFO.SCHW.14.39 – LO: 6-1
United States – BUSPROG: Analytic
The Importance Of Project Schedules
38. In project time management, a(n) _____ is an output of controlling the schedule
a.
activity duration estimate
b.
project management plan update
c.
activity attribute
d.
milestones list
Difficulty: Moderate
INFO.SCHW.14.39 – LO: 6-1
United States – BUSPROG: Analytic
The Importance Of Project Schedules
Bloom’s: Comprehension
39. Which of the following documents is most likely to include planned project start and end dates which serve as the
starting points for a detailed schedule?
a.
Resource breakdown structure
b.
Milestones list
c.
Organizational process assets update
d.
Project charter
plan updates, and project documents updates.
Difficulty: Easy
INFO.SCHW.14.39 – LO: 6-1
United States – BUSPROG: Analytic
The Importance Of Project Schedules
Bloom’s: Knowledge
Chapter 6: Project Time Management
d
1
Difficulty: Easy
p.225
INFO.SCHW.14.40 – LO: 6-2
United States – BUSPROG: Analytic
Planning Schedule Management
Bloom’s: Knowledge
40. Which of the following is a difference between an activity list and an activity attribute?
a.
As opposed to an activity attribute, an activity list provides resource requirements and constraints related to
activities.
b.
An activity list provides a more concrete list of milestones for a project than an activity attribute.
c.
An activity attribute is a tabulation of activities to be included on a project schedule whereas an activity list is
not.
d.
An activity attribute provides more schedule-related information about each activity than an activity list.
d
1
Difficulty: Moderate
p.226
INFO.SCHW.14.41 – LO: 6-3
United States – BUSPROG: Analytic
Defining Activities
Bloom’s: Comprehension
41. A(n) _____ on a project is a significant event that normally has no duration.
a.
milestone
b.
activity attribute
c.
activity sequence
d.
schedule baseline
1
Difficulty: Easy
p.226
Defining Activities
42. In project time management, the main goal of _____ is to ensure that the project team has complete understanding of
all the work they must do as part of the project scope so they can start scheduling the work.
a.
defining activities
b.
estimating activity durations
c.
estimating activity resources
d.
controlling the schedule
1
Difficulty: Moderate
p.226
INFO.SCHW.14.41 – LO: 6-3
United States – BUSPROG: Analytic
Defining Activities
Bloom’s: Comprehension
43. In project time management, the next step after defining project activities is:
a.
planning schedule management.
b.
determining their dependencies.
c.
controlling the schedule.
d.
estimating activity duration.
b
Difficulty: Easy
INFO.SCHW.14.42 – LO: 6-4
United States – BUSPROG: Analytic
Sequencing Activities
Bloom’s: Knowledge
44. Which of the following types of dependencies are inherent in the nature of work being performed on a project?
a.
Mandatory
b.
Discretionary
c.
External
d.
Random
project. They are sometimes referred to as hard logic.
1
Difficulty: Easy
INFO.SCHW.14.42 – LO: 6-4
Bloom’s: Knowledge
45. _____ dependencies are sometimes referred to as soft logic and should be used with care because they may limit later
scheduling options.
a.
Mandatory
b.
Discretionary
c.
External
d.
Inherent
b
1
Difficulty: Easy
p.228
INFO.SCHW.14.42 – LO: 6-4
United States – BUSPROG: Analytic
Sequencing Activities
Bloom’s: Knowledge
46. Which of the following dependencies involve relationships between project and non-project activities?
a.
Mandatory
b.
Discretionary
c.
External
d.
Inherent
1
Difficulty: Easy
p.228
INFO.SCHW.14.42 – LO: 6-4
United States – BUSPROG: Analytic
Sequencing Activities
Bloom’s: Knowledge
47. In an AOA network diagram, _____ occur when two or more activities follow a single node.
a.
combinations
b.
buffers
c.
mergers
d.
bursts
d
1
Difficulty: Easy
p.230
United States – BUSPROG: Technology
Sequencing Activities
Bloom’s: Knowledge
48. A network diagramming technique in which boxes represent activities is known as a(n) _____.
a.
PDM
b.
CPM
c.
ADM
d.
PERT
time relationships.
1
Difficulty: Moderate
p.230
INFO.SCHW.14.42 – LO: 6-4
United States – BUSPROG: Technology
Sequencing Activities
Bloom’s: Knowledge
49. AOA network diagrams use only _____ dependencies.
a.
start-to-start
b.
finish-to-start
c.
finish-to-finish
d.
start-to-finish
b
1
Difficulty: Easy
p.231
INFO.SCHW.14.42 – LO: 6-4
United States – BUSPROG: Technology
Sequencing Activities
Bloom’s: Knowledge
50. Which of the following is a relationship in which the “from” activity cannot start until the “to” activity is started?
a.
Start-to-start
b.
Finish-to-finish
c.
Finish-to-start
d.
Start-to-finish
1
Difficulty: Easy
p.231
United States – BUSPROG: Technology
Bloom’s: Knowledge