9. Establishing a positive relationship with all key stakeholders early in the project helps to create a
desire among those stakeholders to support the project, and builds the communications foundation for
the project.
10. The communications management plan is finalized during project planning, and should only be
changed through a formal change control process.
11. Common purposes for project communications include status reporting and efforts to obtain approval
of project outputs.
12. The primary output of the “Identify Stakeholders” process is the project communications plan.
13. Contemporary project communications typically include both push methods such as blogs, and pull
methods such as voice mail.
14. One common feature of agile projects is the “stand–up meeting”.
15. A stakeholder engagement matrix is a tool that classifies the engagement levels of project
stakeholders, including whether they are unaware, resistant, or supportive.
16. The plan-do-check-act model used to improve processes is also an effective model that project
managers can use to improve project meetings.
17. In order to be sure a project meeting runs according to plan, the project manager should develop an
agenda in advance and deliver it to participants as they arrive at the meeting.