Chapter 5: Developing the Schedule
41. Throughout the performance of the project, some activities will take longer than their estimated duration, others will
be done in less time than their estimated duration, and
a. many will take no time to complete.
b. many will not be completed.
c. others are to be done by two project teams.
d. a few may conform to the estimated duration exactly.
42. With projects for which there is a high degree of uncertainty about the estimated durations for activities, it is possible
to use three time estimates:
a. an original estimate, a petrified estimate, and a most likely estimate.
b. an optimistic estimate, a pessimistic estimate, and a most likely estimate.
c. an optimized estimate, a primary estimate, and a most likely estimate.
d. an opportunity estimate, a pragmatic estimate, and a most likely estimate.