201. Funland Manufacturing Company produces specially machined parts. The parts are produced in batches in
one continuous manufacturing process. Each part is custom produced and requires special engineering design
activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch
production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the
tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and
inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and
providing space. Costs have been assigned to each activity using direct tracing and resource drivers:
Activity drivers for each activity have been identified and their practical capacities listed:
The cost of unit-level activities are assigned using machine hours
The costs of batch-level activities are assigned using number of setups.
The costs of facility-level activities are assigned using machine hours.
Required:
Identify the activities within each process as unit-level, batch-level, product-level, or facility-level.
Build an activity relational table.
Compute the pool rates (round to two decimal places).
Manufacturing process:
Unit-level:
Machining
Batch-level:
Engineering, setups, and inspecting
Product-level:
None
Sustaining process:
Facility-level:
Providing utilities, providing space
Activity
Name
Process
Level
Driver
Capacity
Cost
1
Machining
Manufact.
Unit
Mach. hrs.
50,000
$250,000
2
Engineering
Manufact.
Batch
# of setups
125,000
3
Setup
Manufact.
Batch
# of setups
400
112,500
4
Inspecting
Manufact.
Batch
# of setups
400
100,000
5
Prov. space
Sustaining
Facility
Mach. hrs.
50,000
31,250
6
Prov. util.
Sustaining
Facility
Mach. hrs.
50,000
22,500