156. Figure 4-19
Attraction Corporation produces specially machined parts. The parts are produced in batches in one continuous
manufacturing process. Each part is custom produced and requires special engineering design activity (based on
customer specifications). Once the design is completed, the equipment can be set up for batch production. Once
the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed.
Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition,
there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have
been assigned to each activity using direct tracing and resource drivers:
Activity drivers for each activity have been identified and their practical capacities listed:
The costs of facility-level activities are assigned using machine hours.
Refer to Figure 4-19. What is (are) the unit-level activity(ies)?
157. Batch-level costs are assigned using
158. If activity-based costing is used, electricity usage would be an example of a