59. Which of the following best describes a kill point in the project life cycle?
The period of time given to managers during the feasibility phases to decide on the cost, quality, and time
constraints for the project
A review of the status of a project at each phase of development to determine if it should be continued,
redirected, or terminated
The point of time in the project lifecycle after which it is impossible to terminate a running project
The final submission of the project deliverables after which the project is terminated
INFO.SCHW.14.12 – LO: 2-4
United States – BUSPROG: Analytic
Project Phases and the Project Life Cycle
60. Which of the following best describes outsourcing?
An organization selling its products in a market outside its domestic market
An organization’s acquisition of goods and services from an outside source
An organization setting up manufacturing and retailing facilities in a new country
An organization’s use of virtual teams with employees located in different countries
INFO.SCHW.14.14 – LO: 2-6
United States – BUSPROG: Technology
Recent Trends Affecting Information Technology Project Management
61. Which of the following is a disadvantage of virtual teams as compared to traditional teams?
Increased costs for office space and support
Reduced opportunities for informal transfer of information
Limited flexibility in team working hours
INFO.SCHW.14.12 – LO: 2-4
United States – BUSPROG: Technology
Project Phases and the Project Life Cycle
Bloom’s: Knowledge