OM5 C18
Test Bank
What activity should be crashed first to accelerate the project?
What is the final duration of the fully crashed project?
What is the total crashing cost for the project?
16. A manufacturing company wants to accelerate a project it has underway for a new product
in order to beat its competitors to the market. They use the Critical Path Method (CPM) to
develop the project that has the following activities, durations (in weeks), cost (in dollars), and
precedence relationships:
The three possible paths and durations in the CPM network are :
16
b.
1
d.
The critical path is d-e-f.
The earliest finish time for activity f is 16 weeks.
Per week crashing costs for each activity:
(250 100)/(3 2) = 150/1 = 150
b:
(150 50)/(4 3.5) = 100/.5 = 200
(450 250)/(5 4) = 200/1 = 200
d:
cannot crash
(175 100)/(6 5) = 75/1 = 75*
(600 300)/(7 5) = 300/2 = 150
* Activity e on critical path with least crashing cost
g.
Crashing steps
duration
Activity e from 6 to 5 weeks
Activity f from 7 to 5 weeks
300
h.
Total crashing cost is $375