OM5 C18
Test Bank
b. Activities E and A.
c. Activities A and C.
d. Activities B and D.
13. The county government has decided to redo the street and plans to block the street off
which causes considerable inconvenience to people. The project has three parallel paths defined
as follows: (i) path A-B-C-H to install street lights and electrical wiring that takes 16 days, (ii)
path A-D-E-H to install sidewalks with handicap capabilities that takes 22 days, and (iii) path
A-F-G-H to repave the street including storm drains that takes 30 days. Which one of the
following statements is TRUE?
The expected duration of the project is 30 + 22 + 16 = 68 days.
Path A-B-C-H is the critical path.
Path A-D-E-H has the largest slack time.
Path A-F-G-H is the critical path.
14. The Baker county government has decided to redo the street and plans to block the street off
which causes considerable inconvenience to people. The critical path method (CPM) project
has three sequential (in series, that is “i” is first, then “ii” and finally “iii.”) paths defined as
follows: (i) path A-B-C-H to install street lights and electrical wiring that takes 10 days, (ii)
path G-J-K-L to install sidewalks with handicap capabilities that takes 20 days, and (iii) path U-
V-Z-W to repave the street including storm drains that takes 8 days. Which one of the
following statements is true?
The expected duration of the project is 10 + 20 + 8 = 38 days.
The expected duration of the project is 20 days.
The normal time is inversely related to the crash time.
The three sub-system precedent relationships are in parallel.
15. The critical path method (CPM) work breakdown structure consists of all of the following
EXCEPT:
a. the number and definition of each project activity.
b. the normal time to complete each activity.
c. the immediate predecessors (i.e., the precedent relationships).
d. the probabilities of completing each activity.
16. A project has three parallel paths. A-B-C has a length of 25 days. A-D-C has a length of 15
days. Finally, A-E-C has a length of 20 days. Which one of the following statements is TRUE?
a. A-D-C is the critical path.
b. A-B-C has the most slack.
c. The expected duration of this project is 25 days.