substitution. The quantity variance is the actual quantity used compared with the standard quantity
allowed, with the difference multiplied by the standard price.
The materials variances for several of the parts Maidwell uses are unfavorable. Part #4121
is one item that has an unfavorable variance. Maidwell knows that some of these parts are defective
and will fail. The failure is discovered during production. The normal defective rate is 5 percent
of normal input. The original contract price of this part was $0.285 per unit; thus, Maidwell set
the standard unit price at $0.285. The unit contract purchase price of Part #4121 was increased to
$0.325 from the original $0.285 due to a parts specification change. Maidwell chose not to change
the standard; it treated the increase in price as a price variance. In addition, the contract terms were
changed from payment due in 30 days to a 4 percent discount if paid in 10 days or full payment
due in 30 days. These new contractual terms were the consequence of negotiations resulting from
changes in the economy.
Data regarding the use of Part #4121 during December are as follows.
• Purchases of Part #4121
• Unit price paid for purchases of Part #4121
• Requisitions of Part #4121 from stores for use in products
• Substitution of Part #5125 for Part #4121 to use obsolete
stock (standard unit price of Part #5125 is $0.35)
• Units of Part #4121 and its substitute (Part #5125)
identified as defective
• Standard allowed usage (including normal defective
units) of Part #4121 and its substitute based on output for
the month
Maidwell’s material variances related to Part #4121 for December were reported as follows:
Total materials variances for Part #4121
Bob Speck, the purchasing director, claims the unfavorable price variance is misleading.
Speck says that his department has worked hard to obtain price concessions and purchase discounts
from suppliers. In addition, Speck says engineering changes in several parts have increased their
prices, even though the part identification has not changed. These price increases are not his
department’s responsibility. Speck declares that price variances no longer measure purchasing’s
performance.
Jim Buddle, the manufacturing manager, thinks the responsibility for the quantity variance
should be shared. Buddle states that manufacturing cannot control quality associated with less
expensive parts, substitutions of material to use up otherwise obsolete stock, or engineering
changes that increase the quantity of materials used.
The accounting manager, Mike Kohl, suggests that the computation of variances be
changed to identify variations from standard with the causes and functional areas responsible for