75. How do most firms deal with the risks of projects when making capital budgeting decisions?
a. Projects risks are not considered directly because the weighted average cost of capital (WACC) that is used
as the required rate of return for capital budgeting decisions is based on the riskiness of the firm. As a result,
all projects, no matter their risks, can be evaluated using WACC.
b. Evaluating risk is important only when the projects are similar to the firm’s existing assets.
c. Most firms adjust the discount rates used to evaluate new projects that have significantly different risks than
the risk associated with the firm‘s existing assets.
d. Firms generally increase the required rate of return used to evaluate projects that have significantly different
risks than the risk associated with the firm’s existing assets, regardless of whether the new projects’ risks are
higher or lower.
e. None of the above is a correct answer.
76. Dick Boe Enterprises, an all-equity firm, has a corporate beta coefficient of 1.5. The financial manager is
evaluating a project with an IRR of 21 percent, before any risk adjustment. The risk-free rate is 10 percent, and the
required rate of return on the market is 16 percent. The project being evaluated is riskier than Boe’s average project,
in terms of both beta risk and total risk. Which of the following statements is correct?
a. The project should be accepted because its IRR (before risk adjustment) is greater than its required return.
b. The project should be rejected because its IRR (before risk adjustment) is less than its required return.
c. The accept/reject decision depends on the risk-adjustment policy of the firm. If the firm’s policy were to
reduce a riskier-than-average project‘s IRR by 1 percentage point, then the project should be accepted.
d. Riskier-than-average projects should have their IRRs increased to reflect their added riskiness. Clearly, this
would make the project acceptable regardless of the amount of the adjustment.
e. Projects should be evaluated on the basis of their total risk alone. Thus, there is insufficient information in the
problem to make an accept/reject decision.