NARRBEGIN: SA_113_116
A construction company is preparing for a nine-month project, and will need to develop
a staffing plan. The company can assign up to 30 of its own full-time employees to the
project, and will hire short-term contract employees to make up any shortage in meeting
the personnel requirements. Company employees earn $6,000 per month, while
short-term contract employees make $8,600/month. Contract employees can be
assigned to the project beginning in any month, and their contract period is two months.
The number of workers required for the project by month is shown below:
NARREND
Suppose the bonus for completing the project three months early is $250,000. What
would be the net bonus to the company, after adjusting for any difference in personnel
costs under the accelerated schedule?