Which of the following is not a use of labor standards?
A) labor content of items produced
B) cost and time estimates prior to production
C) crew size and work balance
D) basis of wage-incentive plans
E) All of the above are uses of labor standards.
An assembly line is assigned as follows. Station A- task A, B, and C. Station B- task D.
Station C- task E and F. The task times are 7, 3, 2, 9, 4, and 5 minutes respective to A,
B, C, D, E, and F. (Assume that there is no precedence relationships between the tasks,
ie they can be accomplished in any order)
A. Calculate the efficiency.
B. What would the assignment of tasks to stations be using shortest processing time
(assuming the current maximum station time remains the cycle time)?