Which of the following statements is NOT TRUE regarding the fixed-period system
(FPS)?
a. The time between orders is constant, but the order quantity might vary.
b. An order is time-triggered, not inventory-triggered.
c. The optimal replenishment level includes the demand during the review period, plus
any desired safety stock.
d. When demand is not certain, the FPS addresses stockouts by adding safety stock to
the expected demand during time T + L.
Answer:
The Baker county government has decided to redo the street and plans to block the
street off which causes considerable inconvenience to people. The critical path method
(CPM) project has three sequential (in series, that is “i” is first, then “ii” and finally
“iii.”) paths defined as follows: (i) path A-B-C-H to install street lights and electrical
wiring that takes 10 days, (ii) path G-J-K-L to install sidewalks with handicap
capabilities that takes 20 days, and (iii) path U-V-Z-W to repave the street including
storm drains that takes 8 days. Which one of the following statements is true?
a. The expected duration of the project is 10 + 20 + 8 = 38 days.
b. The expected duration of the project is 20 days.
c. The normal time is inversely related to the crash time.
d. The three sub-system precedent relationships are in parallel.
Answer: