Each R requires 4 of component S; each S requires 3 of part T. The lead time for
assembly of R is 1 week. The lead time for the manufacture of S is 2 weeks. The lead
time for the procurement of T is 6 weeks. The cumulative lead time for R is
__________ weeks.
A) 6
B) 9
C) 12
D) 18
E) 28
Which of the following phrases best describes product focus?
A) low volume, high variety
B) finished goods are usually made to order
C) processes are designed to perform a wide variety of activities
D) high fixed costs, low variable costs
E) raw material inventories are high relative to the value of the product
A facilities manager at a company headquarters once said, “I’d like to use Muther’s
office relationship chart or the load-distance model to solve our layout problems, but
neither tool can optimize. I want the best layout possible.” Discuss.