McInnes/Kerr/VanDuzer: Managing the Law: The Legal Aspects of Doing Business, Fourth Edition
Chapter 11: Discharge and Breach
7) Pavel agreed to build a yacht for Dixie. The yacht was to be delivered to Dixie on July
15 and Pavel was to be paid the total price of $100 000 on the same day. Which of the
following statements is TRUE?
a. If Pavel delivers the yacht, and Dixie pays the price, on July 15, she will be required to
provide him with a signed document called a “novation” that signifies his proper
completion of the agreement.
b. If Pavel delivers the yacht on July 15, but has not stenciled the name Sea Bird on the
back of the boat as he had promised to do, Dixie is certainly entitled to refuse delivery and
withhold the purchase price.
c. If Pavel completes construction of a yacht on July 1, only to see it destroyed by a
hurricane the next day, the contract will be certainly discharged on the basis of self-induced
impossibility if Pavel does not have enough time to build another yacht for Dixie by July
15.
d. If Pavel delivers the frame of the yacht, together with the materials that will be required
to actually complete construction of the boat, he is entitled to have the contract discharged
on the basis of “substantial performance” as long as he compensates Dixie for the price that
she will have to pay to have another person finish the project.
e. If the parties created an entire contract, then, unless and until he completes the project,
Pavel will not be entitled to any payment, even if spent $75 000 trying to perform his
obligations.
8) Corrie contractually agreed to build a house for Ed in exchange for $250 000. After
completing about 75 percent of the project, Corrie ran out of resources and informed Ed
that she could not continue. She therefore abandoned the job, as well as a substantial
amount of materials at the work site. After Corrie left, Ed used the abandoned materials to
finish the job himself. Which of the following statements most likely is TRUE?
a. Corrie is entitled to partial payment on the basis of the doctrine of substantial
performance.
b. Although she is not entitled to be paid for her services, Corrie is entitled to sue on the
contract in order to be paid for the materials that Ed used to complete the project.
c. Because Ed completed the job, Corrie is entitled to have the contract discharged on the
basis of performance.