Operating a facility close to its best operating level is clearly important because
a) it reduces fixed cost
b) it reduces overtime requirements
c) of impact on costs
d) of impact on employees bonuses
e) it increases production
For projects whose activities have probabilistic time estimates, the probability of
completing the project in a specified amount of time is determined by
__________________________.
a) the expected time for the critical path only
b) the standard deviation for the critical path only
c) the expected time and standard deviation for the critical path only
d) the expected times for all paths
e) the expected times and standard deviations for the critical path and paths whose
expected times are close to that of the critical path