13) Consider the following work breakdown structure:
What is the estimated expected (mean) time for project completion?
A.35 weeks
B.39 weeks
C.50 weeks
D.104 weeks
E.105 weeks
14) The local operations manager for the Internal Revenue Service must decide whether
to hire one, two, or three temporary tax examiners for the upcoming tax season. She
estimates that net revenues (in thousands of dollars) will vary with how well taxpayers
comply with the new tax code just passed by Congress, as follows:
If she uses the minimax regret criterion, how many new examiners will she decide to
hire?
A.one
B.two
C.three
D.either one or two
E.either two or three
15) The two general approaches to forecasting are:
A.mathematical and statistical.
B.qualitative and quantitative.
C.judgmental and qualitative.
D.historical and associative.