181) Indiana Co. began a construction project in 2018 with a contract price of $150 million to be
received when the project is completed in 2020. During 2018, Indiana incurred $36 million of
costs and estimates an additional $84 million of costs to complete the project. Indiana recognizes
revenue over time and for this project recognizes revenue over time according to the percentage
of the project that has been completed.
In 2019, Indiana incurred additional costs of $58.5 million and estimated an additional $40.5
million in costs to complete the project. Indiana:
A) Recognized $15 million gross profit on the project in 2019.
B) Recognized $13.5 million gross profit on the project in 2019.
C) Recognized $6 million gross profit on the project in 2019.
D) Recognized $1.5 million gross profit on the project in 2019.
182) Indiana Co. began a construction project in 2018 with a contract price of $150 million to be
received when the project is completed in 2020. During 2018, Indiana incurred $36 million of
costs and estimates an additional $84 million of costs to complete the project. Indiana recognizes
revenue over time and for this project recognizes revenue over time according to the percentage
of the project that has been completed.
Suppose that, in 2019, Indiana incurred additional costs of $63.75 million and estimated an
additional $42.75 million in costs to complete the project. Indiana:
A) Recognized $3.75 million loss on the project in 2019.
B) Recognized $5.25 million gross profit on the project in 2019.
C) Recognized $7.5 million gross profit on the project in 2019.
D) Recognized $1.5 million loss on the project in 2019.