Chapter 4
163. Fowler Company is a job-order costing company that produces customized bicycles. During the month of October,
Fowler had three jobs in process, Jobs 3, 4, & 5. By the end of the month all three jobs had been completed, with Job 3
being sold for $435. The following costs belong to each job:
Job 3 Job 4 Job 5
Direct materials $ 80 $ 75 $ 85
Direct labor 100 110 95
Applied overhead 120 132 114
Total $300 $317 $294
A. Overhead is applied based on direct labor dollars. What is the overhead rate?
B. What rate does Fowler use to price its jobs?
C. What is the gross margin on Job 3?
Chapter 4
164. Jocarro Company has a job costing system. The following items appeared in the Work-in-Process account during
February of the current year:
February 1 balance $ 20,000
Materials placed into production ?
Direct labor (4,000 hours) 120,000
Plantwide overhead applied 96,000
Cost of goods manufactured 400,000
February 28 balance 16,000
Jocarro applies overhead to production on the basis of direct labor hours. Job XX, the only job in process on February 28,
has been charged $10,600 materials cost and has 100 labor hours of direct labor time assigned to it.
Required:
A. Determine the predetermined plantwide overhead rate for Jocarro Company.
B. Determine the amounts of materials, direct labor, and plantwide overhead included in the February 28 work in
process.
C. Determine the amount of materials placed into production during February.
Chapter 4
165. Reed Incorporated uses a job-order costing system and a predetermined overhead rate based on machine hours.
At the beginning of the year, the company estimated manufacturing overhead for the year would be $240,000 and
machine hours would be 8,000.
The following information pertains to December of the current year:
Job 10 Job 11 Job 12 Total
Work-in-process, Dec. 1 $16,000 $26,000 $38,000 $80,000
December production activity:
Materials requisitioned $4,000 $4,800 $7,200 $16,000
Direct labor cost 2,400 3,600 4,000 10,000
Machine hours 400 hrs. 700 hrs. 900 hrs. 2,000 hrs.
Labor hours 120 hrs. 180 hrs. 200 hrs. 500 hrs.
Chapter 4
Actual manufacturing overhead cost incurred in December was $61,000.
Required:
A. Compute the predetermined overhead application rate.
B. Determine the total cost associated with each job.
C. If Jobs 10 and 12 were completed, prepare the journal entry to move the cost.
D. If Job 10 was delivered to customers that paid $50,000 cash, prepare the journal entries.
E. What is the gross margin for Job 10?
F. What is the cost assigned to ending work in process?
G. Assuming no beginning finished goods what is the cost assigned to ending finished goods?
H. How much was overhead over/underapplied?
Chapter 4
166. Budgeted overhead is $60,000, budgeted direct labor hours are 3,000, actual overhead is $64,000, and direct labor
hours are 3,230. Unadjusted cost of goods sold is $135,670.
A. Calculate the overhead variance.
B. What is adjusted cost of goods sold?
167. During February, Alexander, Inc., worked on two jobs with the following data:
Job 12 Job 13
Units in each order 100 units 200 units
Units sold 100 units —
Chapter 4
Materials requisitioned $ 2,480 $ 1,970
Direct labor hours 820 hrs. 1,166 hrs.
Direct labor cost $12,300 $17,490
Overhead is assigned on the basis of direct labor hours at a rate of $12. During February, Job 12 was completed and
transferred to finished goods. Job 13 is the only unfinished job at the end of the month.
A. Calculate the per-unit cost of Job 12.
B. Calculate the ending balance in the work-in-process account.
168. During February, Alexander, Inc., worked on two jobs with the following data:
Job 12
Job 13
Units in each order 100 units 200 units
Units sold 100 units —
Materials requisitioned $ 2,480 $ 1,970
Direct labor hours 820 hrs. 1,166 hrs.
Direct labor cost $12,300 $17,490
Overhead is assigned on the basis of direct labor hours at a rate of $12. During February, Job 12 was completed and
transferred to finished goods. Job 13 is the only unfinished job at the end of the month.
A. Prepare the journal entries for requisitioning all materials used during the month.
B. Prepare the journal entries for direct labor for the month. Assume the workers have not been paid yet.
Chapter 4
169. During February, Alexander, Inc., worked on two jobs with the following data:
Job 12 Job 13
Units in each order 100 units 200 units
Units sold 100 units —
Materials requisitioned $ 2,480 $ 1,970
Direct labor hours 820 hrs. 1,166 hrs.
Direct labor cost $12,300 $17,490
Overhead is assigned on the basis of direct labor hours at a rate of $12. During February, Job 12 was completed and
transferred to finished goods. Job 13 is the only unfinished job at the end of the month.
Prepare the journal entries reflecting the completion and sale on account of Job 12. The selling price is 160% of cost.
Chapter 4
170. If actual overhead for the year is $33,451 and applied overhead is $32,000, is the overhead variance overapplied or
underapplied? Prepare the journal entry necessary to reconcile overhead. Assume the variance is immaterial.
171. The following information was taken from the job cost sheet for Job 101 for Scott Manufacturing Company:
Date started: July 5
Date completed: August 21
Direct Direct Factory Job
Date materials labor overhead Total
July 5 $3,000
Chapter 4
July 15 $ 900 $450
July 17 1,500
July 22 1,350 675
August 1 1,500
August 21 600 300
Job 101 was sold on account on August 25 for 160% of its cost.
Required:
A. Prepare summary journal entries to record the costs incurred for Job 101 in the current year for direct materials,
direct labor, and factory overhead.
B. Prepare the journal entry to record the completion of Job 101.
C. What is the predetermined factory overhead rate for Scott?
D. Prepare the journal entries to record the sale of Job 101.
Chapter 4
172. Brady Corporation has estimated overhead to be $250,000 for the year based on an estimated amount of direct labor
hours of 40,000. Actual direct labor hours for the year are 41,500 and actual overhead is $258,900.
Required:
A.) Calculate the predetermined overhead rate.
B.) Calculate how much overhead has been applied.
C.) Calculate the overhead variance.
D.) Assuming that the variance is immaterial, prepare the journal entry to close the variance.
173. Deluxe Design Company makes custom furniture. On December 1, there were two jobs in process, Job 683, with a
cost of $14,200 and Job 684 with a cost of $23,500. Jobs 685, 686, and 687 were started during the month of December.
Data on costs added during the month are as follows:
Job 683 Job 684 Job 685 Job 686 Job 687
Direct materials $11,000 $8,000 $31,400 $16,700 $6,000
Direct labor 21,000 6,000 12,300 8,450 2,500
Overhead is applied to production at the rate of 80% of direct labor cost. Job 685 was completed on December 17. Job
684 was completed on December 21 and the client was billed at cost plus 45%. All other jobs remained in process.
Chapter 4
Required:
A.) Determine the amount of overhead to apply to each job for the period.
B.) Calculate the cost of work-in-process at the end of the month.
C.) Calculate the cost of finished goods, assuming that finished goods inventory on December 1st was zero.
Chapter 4
174. Deluxe Design Company makes custom furniture. On December 1, there were two jobs in process, Job 683, with a
cost of $14,200 and Job 684 with a cost of $23,500. Jobs 685, 686, and 687 were started during the month of December.
Data on costs added during the month are as follows:
Job 683 Job 684 Job 685 Job 686 Job 687
Direct materials $11,000 $8,000 $31,400 $16,700 $6,000
Direct labor 21,000 6,000 12,300 8,450 2,500
Overhead is applied to production at the rate of 80% of direct labor cost. Job 685 was completed on December 17. Job
684 was completed on December 21 and the client was billed at cost plus 45%. All other jobs remained in process.
Required:
A.) The actual overhead for December was $41,100, calculate the variance.
B.) Calculate the sales price for Job #684.
C.) Calculate the adjusted cost of goods sold for the month of December.
D.) If selling and administrative expenses for the month totaled $5,600, what is the company’s operating income for
December?
Chapter 4
175. Deluxe Design Company makes custom furniture. On December 1, there were two jobs in process, Job 683, with a
cost of $14,200 and Job 684 with a cost of $23,500. Jobs 685, 686, and 687 were started during the month of December.
Data on costs added during the month are as follows:
Job 683 Job 684 Job 685 Job 686 Job 687
Direct materials $11,000 $8,000 $31,400 $16,700 $6,000
Direct labor 21,000 6,000 12,300 8,450 2,500
Overhead is applied to production at the rate of 80% of direct labor cost. Job 685 was completed on December 17. Job
684 was completed on December 21 and the client was billed at cost plus 45%. All other jobs remained in process.
Prepare the journal entries to record the following:
A.) Requisitioning of raw materials
B.) Direct labor costs
C.) Applied overhead
D.) Transfer to finished goods
E.) Sale of finished goods (assume sale was made on account)
F.) Closing underapplied/overapplied variance (all variances are immaterial)
Chapter 4
176. Bower Company manufactures a product in a factory that has two producing departments, Cutting and Stitching, and
two support departments, D1 and D2. The activity driver for D1 is number of employees, and the activity driver for D2 is
number of machine hours. The following data pertain to Bower:
Support Departments Producing Departments
D1 D2 Cutting Stitching
Direct costs $210,000 $165,000 $130,000 $78,500
Normal activity:
Number of employees — 40 80 170
Machine hours 800 — 15,000 5,000
Required:
A. Calculate the cost assignment ratios to be used under the direct method for departments D1 and D2.
B. Allocate the support department costs to the producing departments by using the direct method.
Chapter 4
Chapter 4
177. An approach that assigns the actual costs of direct materials and direct labor to products but uses a predetermined
rate to assign overhead costs
178. An approach that assigns actual costs of direct materials, direct labor, and overhead to products
179. A costing system in which costs are collected and assigned to units of production for each individual job
180. A costing system that accumulates production costs by process or by department for a given period of time
Chapter 4
181. Overhead assigned to production using predetermined rates
182. An overhead rate computed using estimated data
183. The amount by which actual overhead exceeds applied overhead
184. The difference between actual overhead and applied overhead
185. The amount by which applied overhead exceeds actual overhead
186. A single overhead rate calculated using all estimated overhead for a factory divided by the estimated activity level
across the entire factory
Chapter 4
187. Estimated overhead for a single department divided by the estimated activity level for that same department
188. The job order number, or name, head this form.
189. This form asks for the type, quantity, and unit price of direct materials.
190. This form is filled out by each employee every day.
Chapter 4
191. Every time a new job is started this is prepared.
192. This form may be used to maintain proper control over a firm’s inventory of direct materials.
193. direct materials, direct labor and applied overhead are totaled to yield manufacturing cost of job
194. the costs of job are transferred from the work-in–process account to finished goods account
Chapter 4
195. actual overhead is reconciled with applied overhead
196. cost of materials is removed from materials account and added to work-in– process account
197. costs of product are removed from finished goods and added to cost of goods sold
198. schedule of costs of goods sold is prepared
199. immaterial overhead variance closed to costs of goods sold