27) Henderson Industrial Products uses a centralized service department for procurement of raw materials, servicing
all three of its divisions-Construction, Manufacturing, and Military. The Construction Division has been allocated a
total of $192,000 of costs from the procurement department. Of that amount, $144,000 is considered traceable to
the three product types within the division-Civil Construction, Residential Construction, and Commercial
Construction. The traceable amounts are further allocated to the three product types within the division as shown
here:
The above information is used to complete a performance report, the divisional income statement, for the
Construction Division. On that report, the divisional segment margin for the whole Construction Division, including
all relevant costs, is:
A) $81,000.
B) $33,000.
C) $48,000.
D) ($15,000).