91) One goal of factoring a project into detailed activities is to
A) decrease the total project cost.
B) decrease the total amount of time devoted to the project.
C) assist in organizing the project’s documentation.
D) assist in assigning individual employees to tasks.
92) The best standard to use in developing estimates for the completion time of systems
development projects in an organization is
A) a vendor-developed standard.
B) an industry-average standard.
C) a standard recommended by a consultant.
D) a standard developed by the organization’s experience.
93) There is no general agreement of standard project phases and tasks in current project
management literature and therefore there are no commonly accepted time estimates or standard
processing rates. However, there is agreement as to several points related to the estimation
process. Which of the following is not an agreed-upon point in the estimation process?
A) Estimates are only estimates no matter how well thought out.
B) Initial estimates regarding time and costs are almost always too high.
C) The accuracy of estimation improves considerably as a project proceeds toward completion.
D) Costs are frequently higher than originally estimated.
94) Which of the following is not an aspect of good project control?
A) Setting measurable goals for each phase and task in the overall project
B) Reporting actual performance against the established project goals
C) Establishing and revising estimates of system utilization
D) Evaluating any significant deviations from the project plan