6) If a project has a net present value equal to zero, then:
A) the initial cost of the project exceeds the present value of the project’s subsequent cash flows.
B) the internal rate of return exceeds the discount rate.
C) the project produces cash inflows that exceed the minimum required inflows.
D) any delay in receiving the projected cash inflows will cause the project’s NPV to be negative.
E) the discount rate exceeds the internal rate of return.
7) Net present value:
A) cannot be relied upon when deciding between two mutually exclusive projects.
B) rule for project acceptance must be modified when comparing projects of varying sizes.
C) is less commonly used in business than the profitability index method of analysis.
D) is not as widely used in practice as payback and discounted payback.
E) provides the means for considering the risks associated with a specific project.
8) A project has an initial cost of $26,000, a discount rate of 11.7 percent, a life of 5 years, and
an NPV of $11,216. Given this, you know that the project is expected to earn a return:
A) equal to 11.7 percent of $26,000 plus an additional $11,216.
B) of $11,216 in total.
C) equal to 11.7 percent of $37,216 (= $26,000 + 11,216).
D) of 11.7 percent of $11,216.
E) of $26,000 minus $11,216.