CHAPTER 14: COST CONTROL
(Difficulty: E = easy, M = medium, H = hard)
(E) 1. If the schedule variance is positive and the cost variance is negative, the project’s
status is:
A. Over budget and behind schedule
(E) 2. The EVMS term that represents the value of work actually accomplished is:
D. BAC
(M) 3. Which of the following terms is used to determine the trend on cost?
D. AC
(M) 4. If PV = $100, EV = $200, and AC = $300, the status is:
D. Under budget and ahead of schedule
(H) 5. If SPI = 1.05 and CPI = 0.96, the project’s trend is:
D. Under budget and ahead of schedule
(H) 6. Consider the following: BAC = $1000, VAC = <$200>, and AC = $400. Therefore,
EV = _____.
C. $800
D. Cannot be determined