CHAPTER 13: PRICING AND ESTIMATING
(Difficulty: E = easy, M = medium, H = hard)
(E) 1. Which of the following is a cost-estimating relationship?
(E) 2. Which of the following standard project estimating techniques is usually accomplished
in weeks?
A. Parametric
(M) 3. Pricing out the construction cost of a home by a cost per square foot would be
representative of a ____________ estimate.
D. Grassroots
(M) 4. When a functional manager tells you that your project is 10% more difficult than the
standard project, the functional manager is providing you with a _____ estimate.
D. Grassroots
(E) 5. Which of the following projects would most likely have reasonably good estimating
techniques?
D. New product development
(M) 6. Material provided in a proposal to justify one’s estimates are called:
A. Supporting pricing