(M) 21. A customer is unhappy with the performance thus far on a project. The customer states
that, unless scope changes are made at the contractor’s expense, the contractor would
be removed from the customer’s preferred bidders list for future contracts. The
contractor would most likely:
A. Refuse to perform the scope changes.
(H) 22. During the execution of a project, the customer asks you to perform additional tests,
which the customer will pay for. Unfortunately, there are no resources available to
perform the additional tests. The project manager should:
A. Refuse to perform the tests.
(M) 23. Project sponsors within the contractor’s company have the authority to change the
scope of an external customer’s project as they see fit.
(M) 24. During competitive bidding, a contractor can submit inclusions and exclusions to the
customer’s preliminary statement of work.
(H) 25. During an interface meeting with your customer, the two of you have different
interpretations of the raw data. If the customer’s interpretation is correct, then the
direction of the project should change. However, the customer states that they need
D. Cancel the project and then, after an agreement is reached, submit a new proposal
and price to restart the project.