(E) 17. Which of the following problems affects the functional manager’s ability to staff and
support a project during execution?
(H) 18. What type of project manager would have employees (i.e., team members) that report
directly to the project manager full-time for the duration of the project?
A. Lightweight team leader
(H) 19. When team members take direction from both the project and line managers, the type
of project manager is usually a:
A. Lightweight team leader
(H) 20. On a project headed up by a lightweight project manager, employees have their
performance reviews made by:
D. Project managers only
(H) 21. Which of the following is normally not part of a team member’s role?
D. Completing the work at the earliest possible time.