15) Using the information in Table J.17 and Johnson’s rule, what is the makespan for these seven jobs?
A) 58 days or greater
B) greater than or equal to 55 days but less than 58 days
C) greater than or equal to 52 days but less than 55 days
D) less than 52 days
16) Using the information in Table J.17 and Johnson’s rule, how much idle time does Team 2 have from
the start of the first project through completion of the seventh?
A) 2 days
B) 3 days
C) 4 days
D) 5 days
17) Using the information in Table J.17 and Johnson’s rule, develop a schedule that minimizes makespan
for these seven jobs. Assume that job C could be neatly split into two equal parts, each having half of the
processing time on each machine as the full job C. Using your original sequence, but splitting job C, what
is the makespan for the seven jobs?
A) between 58 and 59 days
B) between 56 and 57 days
C) between 55 and 56 days
D) between 57 and 58 days