25) Using Table 7.14, what is the probability of completing the project in 29 or fewer weeks?
A) less than or equal to 40%
B) greater than 40% but less than or equal to 45%
C) greater than 45% but less than or equal to 50%
D) greater than 50%
26) Using Table 7.14, what is the probability that the project will take 16 or more weeks to complete?
A) less than or equal to 20%
B) greater than 20% but less than or equal to 25%
C) greater than 25% but less than or equal to 30%
D) greater than 30%
27) Using Table 7.14, if the expected time for activity C is changed to 12 weeks, by how many weeks will
the project’s expected completion time increase?
A) It will not change.
B) It will increase by one week.
C) It will increase by two weeks.
D) It will increase by three weeks.
28) Assuming a beta distribution is being used, if the most pessimistic time for an activity increases by six
weeks, what will happen to the expected time for that activity?
A) It will increase by one week.
B) It will decrease by one week.
C) It will increase by six weeks.
D) It will remain the same.