37) Using Table 7.9, if the project completion time has to be reduced by one week, which of the following
activities should be crashed to minimize the extra cost of earlier completion?
A) Activity B
B) Activity E
C) Activity H
D) Activity J
38) Using Table 7.9, what is the difference, in dollars, between the minimum-time schedule and the
schedule created by crashing all activities to their limits? Assume that there are no indirect or penalty
costs.
A) less than or equal to $1,000
B) greater than $1,000 but less than or equal to $2,000
C) greater than $2,000 but less than or equal to $3,000
D) greater than $3,000
39) Using Table 7.9, if the project’s normal earliest completion time is to be reduced by two weeks, what is
the minimum additional cost that will be incurred in achieving this two-week reduction?
A) less than or equal to $1,000
B) greater than $1,000 but less than or equal to $1,500
C) greater than $1,500 but less than or equal to $2,000
D) greater than $2,000