5) A project has three paths. A–B-C has a length of 25 days. A–D-C has a length of 15 days. Finally, A–E-C
has a length of 20 days. Which one of the following statements is true?
A) A-D-C is the critical path.
B) A-B-C has the most slack.
C) The expected duration of this project is 25 days.
D) The expected duration of this project is 25 + 15 + 20 = 60 days.
6) The earliest start time for an activity is equal to the:
A) smallest earliest finish time of all of its immediate predecessors.
B) largest earliest finish time of all of its immediate predecessors.
C) smallest late start time of any of its immediate predecessors.
D) largest late finish time of all of its immediate predecessors.
7) Assume that activity G has the following times:
Early start time = 7 days
Early finish time = 13 days
Late start time = 15 days
Late finish time = 21 days
Which of the following statements is true about activity G?
A) Activity G takes 14 days to complete.
B) Activity G has a slack time of 8 days.
C) Activity G is on the critical path.
D) Activity G takes 2 days to complete.