39) A technique used for projecting time-phased capacity requirements for workstations is called:
A) capacity requirements planning.
B) time-adjusted output control.
C) input-output control.
D) work center planning.
40) Which of the following is not one of the uses of MRP in promoting a healthy environment?
A) An MRP system can track waste in a bill of materials as a component of an item.
B) When the master production schedule is developed for a product, reports can be generated that project
the quantity of waste.
C) When the master production schedule is developed for a product, reports can be generated that project
the timing of waste.
D) The MRP system can be used to communicate directly with the International Organization for
Standardization to file ISO 9000 documentation.
41) Which best defines the gross requirements for a component item?
A) the forecasted customer demand for the component
B) the amount of safety stock needed to buffer against uncertainties
C) the sum of gross requirements for all parents of the component
D) the total demand for the component derived from all immediate parents