7) Flow time is only the time a job spends being processed, and excludes any time waiting to be
processed, equipment set up time and time spent moving between operations.
8) Advanced planning and scheduling systems (APS) seek to optimize resources across the supply chain
and align daily operations with strategic goals.
9) The workforce schedule:
A) determines when employees work.
B) determines how many workers are needed over an extended horizon.
C) determines the daily worker requirements.
D) specifies the specific task each worker is to do and when.
10) Gantt charts can be used to:
A) monitor the progress of jobs but cannot be used to sequence work on each machine.
B) sequence work on each machine but cannot be used to monitor the progress of each job.
C) monitor the progress of jobs and sequence work on each machine.
D) monitor the average number of defective parts generated by a machine on each job.