page-pf1
79) What would be the estimated time for completion if the time estimates for report design are
as follows? optimistic = 3 weeks; pessimistic = 9 weeks; realistic = 6 weeks
A) 3 weeks
B) 5 weeks
C) 36 weeks
D) 6 weeks
E) 18 weeks
Gantt charts and network diagrams.
CLLO: Discuss best practices for selecting, evaluating, and managing information systems
projects, Explain how information systems can be used to assist in decision making
Classification: Application
AACSB: Information Technology, Application of Knowledge
80) What would be the estimated time for completion if time estimates for programming are as
follows? optimistic = 4 weeks; pessimistic = 6 weeks; realistic = 5 weeks
A) 5 weeks
B) 6 weeks
C) 15 weeks
D) 3 weeks
E) 30 weeks
Gantt charts and network diagrams.
CLLO: Discuss best practices for selecting, evaluating, and managing information systems
projects, Explain how information systems can be used to assist in decision making
Classification: Application
AACSB: Information Technology, Application of Knowledge
81) What would be the estimated time for completion if time estimates for installation are as
follows? optimistic = 1 week; pessimistic = 1 week; realistic = 1 week
A) 5 weeks
B) 12 weeks
C) 6 weeks
D) 3 weeks
E) 1 week
Gantt charts and network diagrams.
CLLO: Discuss best practices for selecting, evaluating, and managing information systems
projects, Explain how information systems can be used to assist in decision making
Classification: Application
AACSB: Information Technology, Application of Knowledge
29
page-pf2
82) Which of the following is true regarding Gantt chart construction?
A) Squares are used to represent activities.
B) To construct the Gantt chart, a horizontal bar is drawn for each activity that reflects its
sequence and duration.
C) To show precedence relationships, arrows are used to connect the nodes.
D) Arrows are used to reflect the sequence of activities.
E) Ellipses are used to represent activities.
Gantt charts and network diagrams.
CLLO: Discuss best practices for selecting, evaluating, and managing information systems
projects, Explain how information systems can be used to assist in decision making
Classification: Application
AACSB: Information Technology, Application of Knowledge
83) Which of the following is NOT a true statement regarding network diagrams?
A) All activities with a slack time equal to zero are on the critical path.
B) Nodes not on the critical path can be delayed (for some amount of time) without delaying the
final completion of the project.
C) The latest expected completion time refers to the time in which an activity can be completed
without delaying the project.
D) To construct a network diagram, a horizontal bar is drawn for each activity that reflects its
sequence and duration.
E) The critical path of a network diagram is represented by the sequence of connected activities
that produce the longest overall time period.
Gantt charts and network diagrams.
CLLO: Discuss best practices for selecting, evaluating, and managing information systems
projects, Explain how information systems can be used to assist in decision making
Classification: Application
AACSB: Information Technology, Application of Knowledge
30
page-pf3
84) The amount of time that an activity can be delayed without delaying the project refers to:
A) noncritical time.
B) slack time.
C) down time.
D) delay time.
E) stop time.
Gantt charts and network diagrams.
CLLO: Discuss best practices for selecting, evaluating, and managing information systems
projects, Explain how information systems can be used to assist in decision making
Classification: Application
AACSB: Information Technology, Application of Knowledge
85) Slack time is equal to:
A) the difference between an activity's latest and earliest expected completion time.
B) the latest expected completion time.
C) the difference between the start time and realistic time for each activity.
D) the sum of an activity's latest and earliest expected completion time.
E) the difference between the optimistic time and pessimistic time for an activity.
Gantt charts and network diagrams.
CLLO: Discuss best practices for selecting, evaluating, and managing information systems
projects, Explain how information systems can be used to assist in decision making
Classification: Application
AACSB: Information Technology, Application of Knowledge
86) Which of the following slack times indicates that an activity is on the critical path?
A) 1
B) 10
C) 0
D) 2
E) 5
Gantt charts and network diagrams.
CLLO: Discuss best practices for selecting, evaluating, and managing information systems
projects, Explain how information systems can be used to assist in decision making
Classification: Application
AACSB: Information Technology, Application of Knowledge
31
page-pf4
87) Which of the following refers to the time in which an activity can be completed without
delaying the project?
A) Latest expected completion time
B) Earliest expected completion time
C) Delay time
D) End time
E) Critical time
Gantt charts and network diagrams.
CLLO: Discuss best practices for selecting, evaluating, and managing information systems
projects, Explain how information systems can be used to assist in decision making
Classification: Application
AACSB: Information Technology, Application of Knowledge
88) Automated tools available to help you manage a development project are referred to as:
A) diagram generators.
B) project management software.
C) systems development software.
D) desktop publishing software.
E) utility software.
Gantt charts and network diagrams.
CLLO: Discuss best practices for selecting, evaluating, and managing information systems
projects, Explain how information systems can be used to assist in decision making
Classification: Application
AACSB: Information Technology, Application of Knowledge
32
page-pf5
89) An example of a project management system is:
A) Word Perfect.
B) Microsoft Office.
C) Microsoft Project for Windows.
D) Lotus 1-2-3.
E) QuarkXpress.
Gantt charts and network diagrams.
CLLO: Discuss best practices for selecting, evaluating, and managing information systems
projects, Explain how information systems can be used to assist in decision making
Classification: Application
AACSB: Information Technology, Application of Knowledge
90) Briefly define and compare Gantt and Network diagrams.
Gantt charts and network diagrams.
CLLO: Discuss best practices for selecting, evaluating, and managing information systems
projects, Explain how information systems can be used to assist in decision making
Classification: Application
AACSB: Information Technology, Application of Knowledge
33
page-pf6
91) Identify and briefly discuss the four phases involved in managing a project.
CLLO: Discuss best practices for selecting, evaluating, and managing information systems
projects
Classification: Concept
AACSB: Information Technology, Application of Knowledge
92) Briefly discuss project management software.
CLLO: Discuss best practices for selecting, evaluating, and managing information systems
projects
Classification: Concept
AACSB: Information Technology, Application of Knowledge
34
page-pf7
93) Identify the common activities and skills of a project manager.
CLLO: Discuss best practices for selecting, evaluating, and managing information systems
projects
Classification: Concept
AACSB: Information Technology, Application of Knowledge
94) What is a project? Who is the project manager?
CLLO: Discuss best practices for selecting, evaluating, and managing information systems
projects
Classification: Concept
AACSB: Information Technology, Application of Knowledge