70) Ensuring that all contractual terms of the project have been met is done during:
A) conducting postproject reviews.
B) closing the customer contract.
C) setting a baseline project plan.
D) communicating the project status.
E) project implementation.
CLLO: Discuss best practices for selecting, evaluating, and managing information systems
projects
Classification: Concept
AACSB: Information Technology, Application of Knowledge
71) Determining the strengths and weaknesses of project deliverables, the processes used to
create them, and the project management process is done during:
A) conducting postproject reviews.
B) closing down the project.
C) establishing the communication plan.
D) communicating the project status.
E) closing the customer contract.
CLLO: Discuss best practices for selecting, evaluating, and managing information systems
projects
Classification: Concept
AACSB: Information Technology, Application of Knowledge
72) Any person, group of people, piece of equipment, or material used in accomplishing an
activity is referred to as a(n):
A) entity.
B) agent.
C) resource.
D) identifier.
E) expense.
CLLO: Discuss best practices for selecting, evaluating, and managing information systems
projects
Classification: Concept
AACSB: Information Technology, Application of Knowledge
73) A scheduling technique where the order and duration of the sequence of activities directly
affect the completion date of a project refers to:
25