29. A normal distribution is usually used to describe the form of the probability distribution of
activity durations in the PERT three-estimate approach.
30. If the variance of an activity duration is equal to 1 then all the durations are the same.
31. A manager has decided that an activity has a pessimistic estimate of 15 days, a most-likely
estimate of 6 days, and an optimistic estimate of 3 days. The expected duration of this activity
is 6 days.
32. The mean critical path is the path through the project network that would be the critical
path if the duration of each activity equals its mean.
33. The standard deviation of the critical path is equal to the sum of the standard deviations of
all the activities on the critical path.
34. In order to determine the probability of timely project completion, it is sometimes
necessary to take into account paths other than the critical path.
35. When calculating the probability that a project will finish by a certain time, the
approximation that is obtained is usually lower than the true probability.